Aerial photo of Newport High School gymnasium construction.

Community support for the 2020 Capital Bond Project made it possible to start a three-year plan to reshape, remodel and rebuild several Newport High School campus areas. The project continues, with several phases completed over the past few months.

Recent progress includes:

  • Expanded west parking lot is complete.
  • Rerouting of numerous underground utility lines was completed, enabling construction of the new gymnasium/athletic space to begin.
  • Steel erection is underway for the gymnasium.

Ongoing site work of the project continues. Future phases of work include:

  • New Career and Technical Education labs
  • Additional music rooms
  • Drama spaces
  • Robotics lab
  • Additional general education classrooms
  • Food service area
  • Expanded student commons area