Pink box indicates the new athletic facilities. The gold area will remain a closed construction zone for the next three years.

 

Three-year construction project begins next week

Newport High School will remain open throughout the three-year construction project that begins next week.

 

To keep you up to date throughout the process, we’ve established a fixed place on our website where you can go for information about any closures, relocations, rescheduling that may be necessary.

 

A key thing to know for summer 2022

Many of our student activities (athletics practices, back-to-school events, etc.) will be relocated.

  • Check with coaches (contact info on our website) for the most up-to-date locations for sports.
  • Watch postal and email for instructions as Taking Care of Business Day and other events approach.

The following summary is similar to the one you will find anytime on our website.

 

Summer 2022 Expected Timeline & Changes to Regular Operations

Date Affected Area Description
Summer 2022

June

July

August

Entire Campus
  • Establish safe construction zones
  • Move utility supply lines
  • Move portable classrooms from south side to north side of main buildings; Install restroom portable.
  • Create safe exit pathways that avoid construction
  • Staff parking closed for the summer
  • South access loop by old portables is closed permanently
Athletics Facilities

 

 

 

  • Some fall sports practices & competitions relocated to various high schools. Please locate coach contact information on our Athletics webpage and contact the coach directly for the most up-to-date information for specific teams.
  • Tennis Courts and Stadium Closed for summer.